Recently, as the water insulation bulb in the jacket of hole 36-9 of Zhongjiang Project emerged from the mud, the first concrete pouring of the first pile foundation of No. 36 anti-collision pier of the project department went smoothly and the bottom sealing was successful.
It is reported that the project has completed the construction of a total of 30 bored cast-in-place piles for main piers 31 and 30 and anti-collision piers 38. On October 1, the first pile foundation of No. 36 anti-collision pier was drilled, and the construction of the first pile foundation drilling was completed on October 7. Due to the lack of personnel in the steel bar factory, the production of steel cage is slow. In order to ensure the use of steel cage, the project department, while ensuring the normal construction, has transferred some personnel to participate in the production of steel cage in the steel bar factory, and successfully completed the task, which has been praised by the owner, Party A and supervision.
In the next step, all the staff of the project department will continue to work hard to ensure the completion of the remaining 4 anti-collision piers on schedule under the premise of ensuring the safety, civilized construction and project quality.